Improvements to drainage at Foley's municipal airport are moving forward after Foley City Council approved a construction contract and accepted federal and state funding for the project.
The …
This item is available in full to subscribers.
Please log in to continue |
Improvements to drainage at Foley's municipal airport are moving forward after Foley City Council approved a construction contract and accepted federal and state funding for the project.
The council accepted a bid from RH Deas Co. to improve airport drainage at Holk Field at the Foley Airport. The company's bid of $249,971 was the lowest submitted for the work.
Council members also voted to accept grants from the Federal Aviation Administration (FAA) and the Alabama Department of Transportation's (ALDOT) Aeronautics Bureau to help fund the drainage improvements. The FAA will provide $287,000 while ALDOT will contribute $7,553. The grants are expected to cover about 90% of the project's cost.
Rachel Keith, Foley airport manager, said Public Works Department crews have already completed some drainage improvements, but additional work is needed.
The project area is located in the airport's northeast quadrant and extends north from Peachtree Avenue to the Magnolia River, where the drainage system crosses airport property.
Planned improvements include regrading the area, installing concrete sidewalls at the drainage outfall from Peachtree and reinforcing drainage channel sides with rock where needed.
In separate action, the council accepted additional FAA and ALDOT grants that will provide the final reimbursement for costs associated with an eight-unit T-hangar constructed at the airport in 2024. The city will receive more than $140,000 to complete payment for the hangars.
The council also approved seeking grant funding to replace the airport's current terminal as city officials continue planning for a new facility.
Mayor Ralph Hellmich said the proposed terminal project is not tied to expanding airport services or adding commercial airline flights. Instead, the effort is focused on replacing the aging terminal and providing a new location for the airport's fixed base operator, the company that manages the facility.
"When we say terminal, this is not going to commercial service," Hellmich said. "This is maintaining the current status. Our FBO is in a terminal that's been there for a lot of years. We need this."