The City of Gulf Shores and the new Gulf Shores High School construction project contractor released statements Wednesday afternoon on the Monday morning collapse of a portion of the outdoor sports …

This item is available in full to subscribers.

Subscribe to continue reading. Already a subscriber? Sign in

Get the gift of local news. All subscriptions 50% off for a limited time!

You can cancel anytime.
 

Please log in to continue

Log in

City, contractor release statement on Gulf Shores High School construction collapse

No injuries from incident; City assures building safety

Posted

The City of Gulf Shores and the new Gulf Shores High School construction project contractor released statements Wednesday afternoon on the Monday morning collapse of a portion of the outdoor sports practice pavilion under construction off the Foley Beach Express.

From Rabren General Contractors:

“Evaluations remain underway following an incident on Jan. 27 in which a section of the partially constructed practice pavilion at the new Gulf Shores High School project collapsed. Rabren General Contractors is coordinating closely with officials from the City of Gulf Shores, Volkert, Goodwyn Mills & Cawood, our subcontractors and vendors, third-party adjusters and engineers who are actively investigating the incident. Most importantly, no one was injured, and we are thankful for the swift response of all parties involved. The immediate area around the pavilion will remain cordoned off during the investigation while work on the remainder of the project continues. The affected portion of the project will not impact our ability to complete the project on time, and we plan to remove the debris as soon as we receive approval. Rabren prioritizes the safety of our employees, subcontractors and the public on all our projects. We are committed to maintaining the highest safety and quality standards and will implement all necessary actions based on the investigation’s findings.”

From the City of Gulf Shores:

“Early Monday morning, a portion of the outdoor sports practice pavilion, under construction at the new Gulf Shores High School campus, collapsed. While we are disappointed that this occurred, we are incredibly thankful that no workers were on-site at the time of the collapse and no one was injured. Ensuring the safety of the workers during construction and, ultimately, everyone who will be enjoying the new Gulf Shores High School campus is our highest priority. Currently, an independent team of structural engineers is assessing the site to determine the factors that led to the collapse. Once their investigation is complete, the City of Gulf Shores will determine the appropriate next steps based on their findings. We will provide additional information once the cause of the collapse is determined.

“We understand that an incident like this raises questions and concerns about the safety of this facility. While the cause of the collapse has not yet been determined, we want to reassure the public that this facility was designed to a 174 mph wind load rating, will be constructed in strict compliance with building codes, and will be required to pass all inspections from the Alabama Department of Construction Management (ADCM). These inspections occur at critical milestones during and after construction to ensure all State Building Codes are adhered to, and the ADCM will not issue a Certificate of Occupancy for this facility or any other portion of the new Gulf Shores High School until all required inspections have been completed and passed.”